Paragraph 61 I1
England, Wales and Scotland
This paragraph applies to any specified work that includes or is ancillary to any jetty modification comprised in Work No. 10.
When LUL submits for approval under paragraph 60 plans of any specified work to which this paragraph applies it must state whether the work is intended to be temporary or permanent.
If at any time before the completion of construction of the authorised works LUL decides that, contrary to the statement given under sub-paragraph (2), a work to which this paragraph applies should be permanent or temporary, as the case may be, it must without delay apply to the PLA for confirmation of approval of the specified work.
On making any application under this paragraph LUL must provide the PLA with any revised plans of the specified work together with such further information as the PLA may, within 28 days starting with the date on which the application is made, reasonably require.
Any approval of the PLA required under this paragraph must not be unreasonably withheld but paragraph 60(3) applies.
Conditions imposed by the PLA under paragraph 60(3) or sub-paragraph (5) may include (in the case of a permanent work) conditions as to the future ownership and maintenance of the work, and in the absence of appropriate arrangements regarding ownership and maintenance it is reasonable for the PLA to withhold approval under this paragraph.
The removal of any temporary work to which this paragraph applies and any required removal of materials, plant and equipment or making good must be carried out to the reasonable satisfaction, and subject to the supervision (if given), of the PLA.