Paragraph 80 I1
England, Wales and Scotland
Where any specified work involves dredging, the plans submitted under paragraph 78(1) must include the results of laboratory testing of the material to be dredged. This testing must be undertaken by a laboratory which is accredited to the standard required by the MMO and the tests undertaken must be to the standard accepted by the MMO.
Annotations
Commencement
- I1
Sch. 8 para. 80 in force at 15.12.2014, see art. 1