Paragraph 100 Retained apparatusI1

England, Wales and Scotland

(1)

Before commencing construction of a specified work, the undertaker must submit to ESW plans of the specified work and such further particulars available to it as ESW may reasonably require within 28 days of the submission of the plans.

(2)

A specified work must not be constructed except in accordance with such plans as may be approved in writing by ESW or determined under paragraph 110.

(3)

Any approval of ESW required under this paragraph—

(a)

must not be unreasonably withheld or delayed;

(b)

is deemed to have been given if it is neither given nor refused within 42 days of the submission of the plans for approval, or submission of further particulars (where required by ESW under sub-paragraph (1) whichever is the later; and

(c)

may be given subject to such reasonable requirements as ESW may make for the protection of its apparatus taking into account the terms of this Order.

(4)

Any refusal under this paragraph must be accompanied by a statement of the reasons for refusal.