Paragraph 109 OtherI1
England, Wales and Scotland
Any agreement or approval of ESW required under these provisions—
(a)
must not be unreasonably withheld or delayed;
(b)
is deemed to have been given if it is neither given nor refused within 42 days of the date of submission of a request for such agreement or approval, or, in the case of a refusal, if it is not accompanied by a statement of the grounds of refusal; and
(c)
any request for agreement or approval of ESW required under these provisions must be sent to [email protected]. or such other address as ESW may from time to time appoint instead for that purpose and notify to the undertaker in writing.
Annotations
Commencement
- I1
Sch. 15 para. 109 in force at 18.7.2023, see art. 1