Paragraph 28 Soils ManagementI1
England, Wales and Scotland
No phase of the Bulls Lodge substation works may commence until a soils resource management plan (which must be substantially in accordance with the outline soils resource management plan as relevant to construction activities) for that phase has been submitted to and approved by the relevant planning authority.
All construction works associated with the Bulls Lodge substation works must be carried out in accordance with the approved soils resource management plan.
Prior to the completion of any phase of the Bulls Lodge substation works, a soils resource management plan (which must be substantially in accordance with the outline soils resource management plan as relevant to operational activities) for that phase must be submitted to and approved by the relevant planning authority.
The operation of the Bulls Lodge substation works must be carried out in accordance with the approved soils resource management plan.
Annotations
Commencement
- I1
Sch. 2 para. 28 in force at 18.7.2023, see art. 1