Part 4 SPEED LIMITSI1

England and Wales

(1)

Road name and number

(2)

Extent

(3)

Speed Limit

M25 Junction 28 Circulatory CarriagewayThe whole length of the improved M25 Junction 28 circulatory carriageway, for a total distance of 610 metres, as shown on sheet 1 of the speed limits and traffic regulations plans.

National speed limit

(70 miles per hour, as existing limit)

M25 Northbound CarriagewayAlong the length of the improved M25 northbound carriageway, for a total distance of 3720 metres, as shown on sheets 1, 3 and 4 of the speed limits and traffic regulations plans.

National speed limit

(70 miles per hour, as existing limit)

M25 Junction 28 Diverge to Loop RoadAlong the length of the new slip road, from its diverge from the M25 northbound carriageway to point C, for a total distance of 265 metres, as shown on sheet 1 of the speed limits and traffic regulations plans.

National speed limit

(70 miles per hour)

M25 Northbound On-Slip and MergeAlong the length of the improved slip road from the M25 Junction 28 circulatory carriageway to its merge with the M25 northbound carriageway, for a total distance of 1234 metres, as shown on sheets 1 and 3 of the speed limits and traffic regulations plans.

National speed limit

(70 miles per hour)

M25 Northbound Off-Slip and DivergeAlong the length of the improved slip road from its diverge from M25 northbound carriageway to M25 Junction 28 circulatory carriageway, for a total distance of 149 metres, as shown on sheet 1 of the speed limits and traffic regulations plans.

National speed limit

(70 miles per hour, as existing limit)

A12 Eastbound CarriagewayAlong the length of the improved A12 eastbound carriageway from the western-most Order limits to point A, for a total distance of 330 metres, as shown on sheet 1 of the speed limits and traffic regulations plans.50 miles per hour, as existing limit
A12 Eastbound CarriagewayAlong the length of the improved A12 eastbound carriageway between point A and B, for a total distance of 908 metres, as shown on sheet 1 of the speed limits and traffic regulations plans.50 miles per hour
A12 Eastbound CarriagewayAlong the length of the improved A12 eastbound carriageway from point B, for a total distance of 693 metres, as shown on sheets 1 and 2 of the speed limits and traffic regulations plans.

National speed limit

(70 miles per hour, as existing limit)

A12 Eastbound Off-Slip and DivergeAlong the length of the realigned slip road, from its diverge from the A12 eastbound off-slip to the M25 Junction 28 circulatory carriageway, for a total distance of 773 metres, as shown on sheet 1 of the speed limits and traffic regulations plans.50 miles per hour
A12 Eastbound On-Slip and MergeAlong the length of the improved A12 eastbound on-slip from the M25 Junction 28 circulatory carriageway to its merge with the A12 eastbound carriageway, for a total distance of 546 metres, as shown on sheets 1 and 2 of the speed limits and traffic regulations plans.

National speed limit

(70 miles per hour, as existing limit)

M25 Junction 28 Loop Road and MergeAlong the length of the new loop road from point C to its merge with A12 eastbound carriageway for a total distance of 1176 metres, as shown on sheet 1 of the speed limits and traffic regulations plans.50 miles per hour