Schedule 6 LAND IN WHICH NEW RIGHTS ONLY ETC. MAY BE ACQUIREDI1
England and Wales
(1) Plot Reference Number shown on Land Plans | (2) Purpose for which rights over land may be acquired | (3) Relevant part of the authorised development |
|---|---|---|
| Land Plans – Sheet 1 of 4 | ||
| 1/1a | To construct, protect, operate, access and maintain diversion of an existing underground high pressure gas pipeline. To construct, access and maintain drainage works. To construct, operate, access and maintain diversions to existing utilities apparatus. | Work Nos. 6 and 29 and other ancillary development (utilities) |
| 1/3 | To construct, operate, access and maintain diversions to existing utilities apparatus. To construct and maintain a new private means of access. | Work No. 19A and other ancillary development (utilities) |
| 1/6 | To construct, access and maintain drainage works from the new loop road. | Work No. 6 |
| 1/8 | To construct, protect, operate, access and maintain diversion of an existing underground high pressure gas pipeline. | Work No. 29 |
| 1/20 | To construct, access and maintain a new drainage outfall pipe. | Work No. 22 |
| 1/21 | To construct, access and maintain a new drainage outfall pipe. | Work No. 22 |
| 1/22 | To construct, access and maintain a new drainage outfall pipe. | Work No. 22 |
| 1/25 | To install, access, monitor and maintain bird boxes. | Other ancillary development (bird boxes) |
| 1/25a | To install, access, monitor and maintain bird boxes. | Work Nos. 2, 6, 23B, 23D and 26 and other ancillary development (bird boxes and utilities) |
| 1/27 | To install, access, monitor and maintain bird boxes. To construct, access and maintain— (a) improvements to the A12 eastbound off-slip (including Maylands Bridge and Grove culvert); (b) Grove Bridge; and (c) realigned stretches of Weald Brook and Ingrebourne River. To construct, operate, access and maintain diversions to existing utilities apparatus. | Work Nos. 2, 6, 23B, 23D and 26 and other ancillary development (bird boxes and utilities) |
| Land Plans – Sheet 3 of 4 | ||
| 3/15 | To install, access, monitor and maintain bird boxes. | Other ancillary development (bird boxes) |
| 3/17 | To install, access, monitor and maintain bird boxes. | Other ancillary development (bird boxes) |
Annotations
Commencement
- I1
Sch. 6 in force at 6.6.2022, see art. 1