Article 8 Limits of deviationI1
England and Wales
In carrying out the authorised development the undertaker may—
Subject to paragraphs (b), (c) and (d), deviate laterally from the lines or situations of the authorised development shown on the works plans to the extent of the limits of deviation shown on those plans;
in respect of Work Nos. 1(i), 1(l), 1(k), 3(b), 8, 9(c), 9(d), 11, 30, 33, 42, between points A and B, C and D, G and H and I and L only, as shown on the works plans, deviate laterally from the lines or situations of the authorised development shown on the works plans to a maximum of 2.0 metres;
in respect of Work Nos. 1(j) and 1(m) as shown on the works plans, deviate laterally from the lines or situations of the authorised development shown on the works plans to a maximum of 5.0 metres;
deviate vertically from the levels of the authorised development shown on the engineering and structural drawings and sections—
to a maximum of 1 metre upwards or downwards in respect of the construction of the gyratory northern overbridge (F1Work No. 27), gyratory southern overbridge (Work No. 28), A34 southbound underpass (Work No. 13), A33 underpass (Work No. 14), attenuation basin (Work Nos. 1(j) and 1(m)), M3 southern bridge portal gantry (Work No. 36) and bridleway (Work No. 9);
to a maximum of 0.75 metres upwards or downwards in respect of the construction of the retaining walls (Work Nos. 2(d), 12(a), 12(c), 31(a), 32(c), 32(d)), subways (Work Nos. 2(e), 24(a), 24(d), 33(a)), A34 footway/cycleway overbridge (work number 4) and gyratory (Work No. 29);
in respect of any other work comprised in the authorised development, to a maximum of 0.5 metres upwards or downwards,
except that those maximum limits of deviation do not apply where it is demonstrated by the undertaker to the Secretary of State’s satisfaction and the Secretary of State, following consultation with the relevant planning authority and the local highway authority, certifies accordingly, that a deviation in excess of those limits would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
Annotations
Textual amendments
- F1
Words in art. 8(d) substituted (10.10.2024) by The M3 Junction 9 Development Consent (Correction) Order 2024 (S.I. 2024/1020), art. 1, Sch.
Commencement
- I1
Art. 8 in force at 9.10.2024, see art. 1 (as amended by S.I. 2024/1020, Sch.)