The M5 Junction 10 Development Consent (Correction) Order 2025
S.I. 2025/1136 · Made 29 October 2025
INFRASTRUCTURE PLANNING
Made 29th October 2025
Coming into force 3rd November 2025
The M5 Junction 10 Development Consent Order 2025f1 (“the 2025 Order”) which granted development consent within the meaning of the Planning Act 2008f2 (“the Act”), contained correctable errors within the meaning of paragraph 1(3) of Schedule 4 to the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received written requests from the applicantf3 and National Highways for the correction of errors in the 2025 Order.
In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State informed the relevant local planning authorities for the area in which the land to which the 2025 Order relates is situated, that the requests had been received.
The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraph 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.
Annotations to the whole text
Footnotes
- f1
- f2
-
2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20).
- f3
-
The term “applicant” is defined in paragraph 4 of Schedule 4 to the Planning Act 2008.
Contents
- 1Citation and commencement
- 2Corrections to the M5 Junction 10 Development Consent Order 2025 (“the 2025 Order”)
- Signature
- Schedule CORRECTABLE ERRORS
- Explanatory note
1Citation and commencement
This Order may be cited as the M5 Junction 10 Development Consent (Correction) Order 2025 and comes into force on 3rd November 2025.
2Corrections to the M5 Junction 10 Development Consent Order 2025 (“the 2025 Order”)
The 2025 Order is corrected as set out in the table in the Schedule, where—
column 1 sets out where the correction is to be made;
column 2 sets out how the correction is to be made; and
column 3 sets out the text to be substituted, inserted or omitted.
Signature
Signed by authority of the Secretary of State for Transport
Samantha Collins-Hill
Deputy Director, Transport Planning
Department for Transport
29th October 2025
CORRECTABLE ERRORS
| (1) Where the correction is to be made | (2) How the correction is to be made | (3) Text to be substituted, inserted or omitted |
| Part 3, Article 11(5) | For “42 days” substitute | “28 days” |
| Schedule 2, paragraph 11(3)(a) | For “relevant planning authority” substitute | “Secretary of State“ |
| Schedule 10 | In relation to the “environmental statement - appendix 1.1: glossary” for “0” substitute | “1” |
| Schedule 10 | In relation to the “environmental statement - appendix 1.2: scoping opinion responses” for “0” substitute | “1” |
Explanatory note
(This note is not part of the Order)
This Order corrects errors and omissions in the M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), a development consent order under the Planning Act 2008, following two requests under paragraph 1(6)(a) of Schedule 4 to that Act.