OpenLegislation

Paragraph 15 Noise MitigationI1

England and Wales

(1)

No part of the authorised development is to commence until written details of proposed noise mitigation in respect of the use and operation of that part of the authorised development, including noise barriers and any very low noise surfacing, have been submitted to and approved in writing by the relevant planning authority following consultation with the county planning authority and the strategic highway authority on matters related to their functions.

(2)

The written details referred to in sub-paragraph (1) must either—

(a)

reflect the mitigation measures included in chapter 6 (noise and vibration) of the environmental statement and the noise and vibration management plan approved as part of the EMP (2nd iteration) pursuant to paragraph 3 of this Schedule; or

(b)

where the mitigation proposed materially differs from the mitigation identified in the environmental statement and the noise and vibration management plan, the undertaker must provide evidence with the written details submitted that the mitigation proposed would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement taking into account the mitigation identified in it.

(3)

The noise mitigation must be constructed in accordance with the approved details referred to in sub-paragraph (1) and must be retained thereafter.

Annotations

Commencement

I1

Sch. 2 para. 15 in force at 25.6.2025, see art. 1