Paragraph 30 Defects PeriodI1
England and Wales
The undertaker must, at its own expense, remedy any defects in the strategic road network as are reasonably required by National Highways to be remedied during the defects period. All identified defects must be remedied in accordance with the following timescales—
in respect of matters of urgency, within 24 hours of receiving notification for the same (urgency to be determined at the discretion of National Highways);
in respect of matters which National Highways considers to be serious defects or faults, within 14 days of receiving notification of the same; and
in respect of all other defects notified to the undertaker, within 4 weeks of receiving notification of the same.
Following the issuing of the provisional certificate, National Highways has responsibility for routine maintenance of the strategic road network save for any soft landscaping works which must be established and which must thereafter be maintained for a period of 5 years by and at the expense of the undertaker.