Paragraph 36 Maintenance of the specified worksI1

England and Wales

(1)

The undertaker must, prior to the commencement of any works of maintenance to the specified works, give National Highways 28 days’ notice in writing of the date on which those works will start unless otherwise agreed by National Highways, acting reasonably.

(2)

If, for the purposes of maintaining the specified works, the undertaker needs to occupy any road space, the undertaker must comply with National Highways’ road space booking requirements and no maintenance of the specified works for which a road space booking is required shall commence without a road space booking having first been secured.

(3)

The undertaker must comply with any requirements that National Highways may notify to the undertaker, such requirements to be notified to the undertaker not less than 7 days’ in advance of the planned commencement date of the maintenance works.

(4)

The provisions of paragraph 28 (opening) shall apply to the opening of any part of the strategic road network following occupation of any road space under this paragraph.

Annotations

Commencement

I1

Sch. 9 para. 36 in force at 25.6.2025, see art. 1