Paragraph 10 Traffic ManagementI1

England and Wales

(1)

No part of the authorised development is to commence until for that part a traffic management plan, which is substantially in accordance with the outline traffic management plan for that part of the authorised development, has been submitted to and approved in writing by the Secretary of State, following consultation with the local highway authority on matters related to its function.

(2)

The authorised development must be carried out in accordance with the traffic management plan approved under sub-paragraph (1).

(3)

In this paragraph, “outline traffic management plan” means the document listed in Schedule 10 (certification of plans and documents, etc.) and certified by the Secretary of State as the outline traffic management plan for the purposes of this Order under article 41 (certification of plans and documents, etc.).