Regulation 48 I1
United Kingdom
For Article 10, substitute—
“Official control
1The official control of a recycling plant and converter must be performed in accordance with the rules laid down in Regulation (EC) No 882/2004 and must include in particular audits as control technique as specified in Article 10 of Regulation (EC) No 882/2004.
2The official control must verify that the recycling process corresponds to the authorised process and that an effective quality assurance system in accordance with Regulation (EC) No 2023/2006 is in place.
3The authorisation holder must notify the Food Safety Authority about the recycling or manufacturing site in which the authorised recycling process is being applied.”.
Annotations
Commencement
- I1
Reg. 48 in force at 31.12.2020 on IP completion day (in accordance with 2020 c. 1, Sch. 5 para. 1(1)), see reg. 1