Paragraph 37 Manner of erection and installation

(1)

Every beltweigher must be positioned so as to facilitate cleaning and testing.

(2)

The installation of a beltweigher must be so designed that an automatic weighing operation will be the same for testing as for a transaction.

(3)

Every beltweigher must be erected in such a way that it is possible to carry out a material test in a place where it is to be used, including in particular the depositing on, or removal from, the belt of material test loads in a reliable and easy manner, without disrupting the normal operation of the beltweigher.

(4)

Any special equipment for the control of the measuring tasks of a beltweigher which is not a permanent fixture of the beltweigher, must be kept in the vicinity of the beltweigher.