In all new and existing ships drills for the operating of watertight doors, sidescuttles, valves, and closing mechanisms of scuppers, ash-shoots and rubbish-shoots, shall take place weekly. In ships in which the voyage exceeds one week in duration a complete drill shall be held before leaving port, and others thereafter at least once a week during the voyage, provided that all watertight power doors and hinged doors, in main transverse bulkheads, in use at sea shall be operated daily.

The watertight doors and all mechanisms and indicators connected therewith, and all valves the closing of which is necessary to make a compartment watertight, shall be periodically inspected at sea, at least once a week.

Notes on Schedule FIRST

Textual amendments

F1

Sch. 1 repealed (1.1.1996) by 1995 c. 21, ss. 314(1), 316(2), Sch. 12 (with s. 312(1), Sch. 14 para. 1)