The Mersey Docks and Harbour Revision (No. 2) Order 1988
S.I. 1988/1973 · Made 9 November 1988
HARBOURS, DOCKS, PIERS AND FERRIES
Made 9th November 1988
Coming into force 10th November 1988
The Secretary of State for Transport, in exercise of the powers conferred by section 14 of the Harbours Act 1964f1 and now vested in himf2 and of all other powers enabling him in that behalf and on the application of The Mersey Docks and Harbour Company, hereby makes the following Order:—
Annotations to the whole text
Footnotes
- f1
-
1964 c. 40; section 14 and Schedule 3 were amended by the Transport Act 1981 (c. 56) section 18, and Schedule 6, paragraphs 2 to 4 and 14.
- f2
-
See S.I. 1981/238.
Contents
1Citation and commencement
This Order may be cited as The Mersey Docks and Harbour Revision (No. 2) Order 1988 and shall come into force on 10th November 1988.
The Mersey Docks and Harbour Acts and Orders 1857 to 1988 and this Order may be cited together as the Mersey Docks and Harbour Acts and Orders 1857 to 1988.
2Extension of time
The period now limited by article 9(2) of The Mersey Docks and Harbour Revision Order 1980f1 (extension of period for completion of works) for the completion of the authorised works as defined by section 2(1) of the Mersey Docks and Harbour Board (Ore Berth) Act 1971f2 so far as those works have not already been constructed, is hereby further extended until 31st December 1989.
Signature
Signed by authority of the Secretary of State
J. W. S. Dempster
An Under Secretary in the
Department of Transport
9th November 1988
Explanatory note
(This note is not part of the Order)
This Order extends for one year the time for the completion of the construction of a deep water river berth in the river Mersey to the south of Seacombe Landing Stage adjacent to the Morpeth and Wallasey Docks authorised by section 4 of the Mersey Docks and Harbour Board (Ore Berth) Act 1971 (as extended).
The applicants for the Order are The Mersey Docks and Harbour Company.