Regulation 16 Calculation of budget requirementsI1
England and Wales
For each financial year the Mid Wales CJC must calculate the amounts described in paragraph (2) attributable to—
its strategic planning functions (including an appropriate proportion of administration costs and other overheads), and
its other functions.
The amounts that the CJC must calculate are—
the amount which the CJC estimates it will spend in respect of the financial year in the exercise of its functions (including spending on administration and other overheads);
the amount which the CJC considers appropriate to raise for contingencies arising in respect of the financial year;
the amount which the CJC considers appropriate to be held as a reserve to meet expenditure it considers will be incurred in respect of future financial years;
any amount which the CJC considers is necessary to meet liabilities outstanding in respect of any earlier financial year.
For each financial year, the Mid Wales CJC must also calculate the aggregate of any amounts it estimates it will receive from sources other than the constituent councils and the Brecon Beacons National Park Authority attributable to—
its strategic planning functions, and
its other functions.
In relation to the first financial year, paragraph (6) applies as if, for “31 January in each preceding financial year” there were substituted “31 January 2022”.
Any revised calculations must be agreed at a meeting of the Mid Wales CJC.
Annotations
Commencement
- I1
Reg. 16 in force at 1.4.2021, see reg. 1(2)