OpenLegislation

Paragraph 10 Notice of worksI1

England and Wales

The Authority must give to the engineer 56 days’ notice of its intention to commence the construction of any of the specified or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, CRT may where appropriate arrange for the publication of notices bringing those works to the attention of users of CRT’s network.

Annotations

Commencement

I1

Sch. 10 para. 10 in force at 2.8.2016, see art. 1