Article 4 Maintenance of authorised developmentI1
England and Wales
(1)
National Grid may at any time maintain the authorised development (excluding the UKPN Works), except to the extent that this Order, or an agreement made under this Order, provides otherwise.
(2)
UKPN may at any time maintain the UKPN Works, except to the extent that this Order, or an agreement made under this Order, provides otherwise.
Annotations
Commencement
- I1
Art. 4 in force at 4.10.2024, see art. 1