Paragraph 10 I1
England and Wales
Unless otherwise agreed with the relevant planning authority, all reinstatement planting works referred to in requirement 9 must be implemented at the earliest opportunity and no later than by the first available planting season after that part of the authorised development to which the reinstatement planting works apply is first brought into operational use.
All reinstatement planting works referred to in requirement 9 must be carried out in accordance with the relevant reinstatement planting plan for that stage of the authorised development, unless otherwise approved by the relevant planning authority.
All reinstatement planting works referred to in requirement 9 must be implemented, monitored and maintained in accordance with the ‘Aftercare’ section of the landscape and ecological management plan approved pursuant to requirement 4.
Any trees or hedgerows planted as part of an approved reinstatement planting plan that, within a period of five years after planting (or such other period as is specified in the landscape and ecological management plan approved pursuant to requirement 4), are removed, die or become in the opinion of the relevant planning authority seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless otherwise approved by the relevant planning authority.
Annotations
Commencement
- I1
Sch. 3 para. 10 in force at 4.10.2024, see art. 1