Paragraph 14 I1
England and Wales
Unless otherwise agreed with the relevant planning authority, no stage of the authorised development may commence until, for that stage, a soil management plan prepared in accordance with Chapter 11 of the outline construction environmental management plan (or the final construction environmental management plan if approved pursuant to requirement 4) describing how construction works should be undertaken to minimise effects on the nature and quality of soil has been submitted to and approved by the relevant planning authority.
The construction works for each stage of the authorised development must be carried out in general accordance with the approved soil management plan referred to in sub-paragraph (1), unless otherwise agreed with the relevant planning authority.
Annotations
Commencement
- I1
Sch. 3 para. 14 in force at 4.10.2024, see art. 1