SANDFORD 400/132kV SUBSTATION SANDFORD 400/132kV SUBSTATION
In the District of North Somerset
Work No. 3A — Sandford Substation
Works to construct the Sandford 400/132kV Substation as shown on Works Plan section D, sheet 1, to include—
earthworks to provide a suitable platform for the equipment;
construction of foundations to support all new structures, plant and equipment;
installation of 2 super grid transformers (SGT) to include noise enclosures;
installation of 2 shunt reactors to include noise enclosures;
installation of air or hybrid insulated switchgear, cable sealing ends, post insulators and conductor;
installation of support structures;
installation of 2 overhead electric line landing gantries;
construction of a site drainage system including oil separator and diversion of the existing rhyne;
construction of site access roads including car parking provision;
construction of the substation perimeter fence;
installation of lamp posts for street lighting and other site furniture;
landscaping, gates and fencing of site boundary;
water storage tank;
operational and ancillary buildings;
diesel generator;
semi permanent access road for transformer deliveries including bridge over Tower Head brook; and
temporary pylon LD40A to the north of Sandford 400/132kV Substation to allow a temporary connection between FLT gantry structures LD39A and LD39B in the period before Work No. 1E is complete.
In the District of North Somerset
Work No. 3B — Temporary project office compound
Works to construct a temporary project office compound, at the location shown on Works Plan section D, sheet 1, to include—
temporary car parking, hard standings and roadways;
temporary offices and staff welfare portacabins;
temporary materials, tools and fuel storage areas;
temporary storage of plant and equipment;
wheel cleaning facilities;
security fencing; and
construction and security lighting.