Article 3 Development consent etc. granted by the OrderI1
England and Wales
Subject to the provisions of this Order and to the Requirements to this Order—
National Grid is granted development consent for the authorised development set out in Schedule 1 (authorised development); and
Subject to article 6(4), UK Power Networks is granted development consent for the UK Power Networks works.
National Grid may—
install the authorised development; and
keep installed the above ground electric lines included in the authorised development except those above-ground electric lines included in the UK Power Networks works.
UK Power Networks may—
subject to F1articles 6(2) and 6(4), install the UK Power Networks works; and
keep installed the above-ground electric lines included in the UK Power Networks works.
The authorised development must be constructed, installed and kept installed in the lines and situations shown on the Works Plans in Schedule 2 (plans and drawings), subject to article 5 (limits of deviation) and to the Requirements set out in Schedule 3 (requirements).
Schedule 2 (plans and drawings) has effect.
Annotations
Textual amendments
- F1
Words in art. 3(3)(a) substituted (8.5.2018) by The National Grid (Richborough Connection Project) (Correction) Order 2018 (S.I. 2018/572), art. 1, Sch.
Commencement
- I1
Art. 3 in force at 24.8.2017, see art. 1