In the District of Thanet and the District of Dover In the District of Thanet and the District of Dover

England and Wales

Works to allow the removal of 5.2km of the 132kV PX route overhead electric line commencing at pylon PX60 as shown on Works Plan Sheet 13 and terminating at the Richborough 132kV Substation PX connection as shown on Works Plan Sheet 17 including the removal of 19 pylons and associated conductors, insulators and fittings.

Notes on Schedule 1

Commencement

I1

Sch. 1 in force at 24.8.2017, see art. 1