Paragraph 10 For the benefit of the proposed Broad Oak ReservoirI1
England and Wales
In paragraphs 10 to 17 of this Part of this Schedule—
“Broad Oak Reservoir” means a reservoir in the vicinity of the village of Broad Oak in Kent proposed by SEW;
“Broad Oak Reservoir Construction Works” means works to be carried out by or on behalf of SEW for the construction of the Broad Oak Reservoir including without limitation works to construct the dam structure, to dig and flood the reservoir, all works required in connection with the Scheme for Habitat Creation and Management, access and egress on foot and with vehicles;
“Broad Oak Reservoir Preparatory Works” means works to be carried out by or on behalf of SEW in connection with the construction of the Broad Oak Reservoir including without limitation the drilling of boreholes, the digging of test pits, the carrying out of geomorphological surveys, the digging of trenches, the creation of a river channel, the removal and planting of trees, woodlands, shrubs and other vegetation and access and egress on foot and with vehicles;
“conductor” means a conductor or part of a conductor being part of any 400kV overhead electrical line forming part of the authorised development as shown on the design drawings;
“pylon” means any pylon forming part of the authorised development and including its foundations and the safety clearance zone around it;
“RCP safety requirements” means the requirement that climbable trees must remain 5.3 metres below the conductor and 5 metres away from the anti-climbing devices attached to the pylons and coppiced trees must remain 3.1 metres below the conductor and 5 metres away from the anti-climbing devices attached to the pylons, the 5 metre distance being such as not to assist unauthorised access above the anti-climbing devices attached to the pylons;
“Scheme for Habitat Creation and Management” means a scheme for the creation of new habitat including the diversion of the Sarre Penn River, the creation of a fish pass and new habitat required to enable the construction of the Broad Oak Reservoir which scheme has been approved by the relevant planning authority;
“SEW’s land” means Plot Numbers 356, 358, 359, 360, 361, 362, 363, 364, 365, 366, 368, 369, 370, 373, 374, 375, 376, 377, 378, 379, 380, 381, 382, 383, 384, 386, 387, 388, 391, 392, 393 and 419.
Annotations
Commencement
- I1
Sch. 14 Pt. 5 para. 10 in force at 24.8.2017, see art. 1