Paragraph 12 Reinstatement schemesI1
England and Wales
(1)
Subject to sub-paragraph (2), any land within the Order limits which is used temporarily for construction is to be reinstated to its former condition, or such condition as the relevant planning authority may approve, within six months of completion of the construction of the stage of authorised development for which it was required, or such further time as may be approved by the relevant planning authority.
(2)
The requirement to reinstate the land to its former condition is subject to the provisions of article 28 (temporary use of land by National Grid) and article 29 (temporary use of land by UK Power Networks).
Annotations
Commencement
- I1
Sch. 3 para. 12 in force at 24.8.2017, see art. 1