Explanatory note
England, Wales and Scotland As made
(This note is not part of the Order)
This Order authorises National Grid to undertake works to the national electricity transmission system between the existing substation at Monk Fryston to the existing substation at Osbaldwick. The proposed development is required to provide sufficient transmission capacity to enable the connection of new electricity generation projects in the region, and to carry out all associated works.
The Order also makes provision in connection with the maintenance of the authorised development.
The Order permits National Grid to acquire compulsorily or by agreement, land and rights in land and to use land for this purpose.
A copy of the plans and book of reference referred to in this Order and certified in accordance with article 48 (certification of plans, etc.) of this Order may be inspected free of charge during working hours at the offices of National Grid Electricity Transmission plc, 1-3 Strand, London WC2N 5EH.