OpenLegislation

Paragraph 120 Termination by the Local Health Board where patients’ safety is seriously at risk or where there is risk of material financial loss to Local Health BoardI1

England and Wales

The Local Health Board may serve notice in writing on the contractor terminating the contract forthwith or with effect from such date as may be specified in the notice if—

(a)

the contractor has breached the contract and as a result of that breach, the safety of the contractor’s patients is at serious risk if the contract is not terminated, or

(b)

the contractor’s financial situation is such that the Local Health Board considers that the Local Health Board is at risk of material financial loss.

Annotations

Commencement

I1

Sch. 3 para. 120 in force at 1.10.2023, see reg. 1(2)