Paragraph 9 Continuing application of published guidance and other documentsI1

England and Wales

Where as a consequence of paragraph 11 (standards for out of hours services) or 125 (compliance with legislation and guidance) of Schedule 6 to the GMS Contracts Regulations a contractual term in a GMS contract requires a contractor to meet requirements set out in a document or have regard to, or comply with, guidance published before the appointed day which has effect immediately before that day, that contractual term continues to apply in respect of such documents and guidance on or after the appointed day—

(a)

as if references to a Primary Care Trust or Strategic Health Authority in that document or guidance were to the Board; and

(b)

until such time as the Board, or as the case may be, the Secretary of State, cancels or withdraws the document or guidance.

Annotations

Commencement

I1

Sch. 1 para. 9 in force at 1.4.2013, see reg. 1(1)