Regulation 21 Notice of making temporary orderI1
England and Wales Not yet in force
Not less than 7 days before making a temporary order the National Park authority must publish notice of its intention to make the order—
in a newspaper circulating in the area in which the road to which the order relates is situated; and
on its website.
The notice must state—
the details specified in paragraphs 1 to 4 of Part 1 of Schedule 2;
the reason or purpose for making the order;
where applicable, the alternative routes available for diverted traffic;
the date on which the National Park authority proposes to bring the order into force; and
the duration of the order.
The National Park authority must, on or before the day on which the order is made, give notice of the order to the chief officer of police for the area in which the road to which the order relates is situated.
Within 14 days of making an order, the National Park authority must publish a notice—
in a newspaper circulating in the area in which the road to which the order relates is situated; and
on its website.
The notice under paragraph (4) must state—
the details specified in paragraphs 1 to 4 of Part 3 of Schedule 2;
the date on which the order came into force; and
the matters set out in paragraph (2)(b), (c) and (e).
No provision of a temporary order may come into force before the date on which the National Park authority publishes a notice in accordance with paragraphs (4) and (5).
Annotations
Commencement
- I1
Reg. 21 in force at 1.10.2007, see reg. 1(1)