The Network Rail (Essex and Others Level Crossing Reduction) (Amendment) Order 2023
S.I. 2023/523 · Made 10 May 2023
This Statutory Instrument has been printed to correct errors in S.I. 2022/651 and is being issued free of charge to all known recipients of that Statutory Instrument.
Transport And Works, England
Transport, England
Made 10th May 2023
Coming into force 11th May 2023
The Secretary of State has determined to make an Order giving effect to the proposals comprised in the application with modifications which in the opinion of the Secretary of State do not make any substantial change in the proposals.
The Secretary of State, in exercise of the powers conferred by sections 1 and 5 of, and paragraphs 4 and 7 of Schedule 1 to, the 1992 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2006/1466, as amended by S.I. 2010/439. S.I. 2011/556, S.I. 2011/2085, S.I. 2012/147, S.I. 2012/1658, S.I. 2012/2590, S.I. 2013/755, S.I. 2014/469, S.I. 2015/377, S.I. 2015/627, S.I. 2015/1682, S.I. 2017/979, S.I. 2017/1070 and S.I. 2019/311
- f2
-
1992 c. 42. Section 1 was amended by paragraphs 51 and 52 of Schedule 2 to the Planning Act 2008 (c. 29). Section 5 was amended by S.I. 2012/1659.
Contents
- 1Citation, commencement and interpretation
- 2Citation, commencement and interpretation
- 3Amendments to the 2022 Order
- Signature
- Explanatory note
1Citation, commencement and interpretation
This Order may be cited as the Network Rail (Essex and Others Level Crossing Reduction) (Amendment) Order 2023 and comes into force on 11th May 2023.
2Citation, commencement and interpretation
In this Order, “the 2022 Order” means the Network Rail (Essex and Others Level Crossing Reduction) Order 2022f1.
3Amendments to the 2022 Order
The 2022 Order is amended as follows.
In Part 1 of Schedule 2, in the entry for the Parish of Boreham, in column (3)—
for “P163, P164, P165 and P166” substitute “P163 and P164”; and
for “P163, P167, P165, P166 and P162” substitute “P163, P167 and P165”.
In Schedule 5, in the entry for the Parish of Thorley—
in column (2), omit “32”; and
in column (3) omit “Access”.
Signature
Signed by authority of the Secretary of State for Transport
Natasha Kopala
Head of the Transport and Works Act Orders Unit
Department for Transport
10th May 2023
Explanatory note
(This note is not part of the Order)
This Order amends the Network Rail (Essex and Others Level Crossing Reduction) Order 2022 which conferred powers on Network Rail to close or downgrade the level crossings specified in Schedule 2 and for the permanent acquisition of and temporary use of land in connection with the construction of public rights of way and other works in the highway required in connection with the level crossing changes. This Order clarifies the extent of stopping up of Footpath EX/213/24 (Boreham) (Schedule 2) and removes Plot 32 from Schedule 5 which is no longer needed for access.