Paragraph 12 Ecological Management PlanI1
England, Wales and Scotland
(1)
No stage of the authorised development is to commence until for that stage a written ecological management plan reflecting the survey results and ecological mitigation and enhancement measures included in the Environmental Statement, in particular to accord with Table 1-J, ‘Proposed Mitigation During Construction’ in volume 3, Report 9 (Ecology Technical Report) of the Environmental Statement has been submitted to and approved by the relevant planning authority.
(2)
The ecological management plan must include an implementation timetable and must be carried out as approved.
Annotations
Commencement
- I1
Sch. 1 para. 12 in force at 26.9.2012, see art. 1