Article 3 Closure of Kings Mill No. 1 level crossing

Original text. Later amendments are not shown.

(1)

Subject to paragraph (3), the Kings Mill No. 1 level crossing and the existing bridleway are stopped up and discontinued.

(2)

Subject to paragraph (3), upon the stopping up and discontinuance of the Kings Mill No. 1 level crossing and the existing bridleway any right of way over the Kings Mill No. 1 level crossing is extinguished and any public right of way over the existing bridleway is extinguished.

(3)

Paragraphs (1) and (2) are not to have effect until the new public right of way has been constructed and completed to the reasonable satisfaction of the highway authority in accordance with article 4 (creation and maintenance of new public right of way) and is open for use.

(4)

Any person who suffers loss by the extinguishment of any private right of way over the Kings Mill No. 1 level crossing under this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5)

This article does not apply so as to extinguish the rights of statutory undertakers to maintain their apparatus.