Article 4 Development consent etc. granted by the OrderI1
England, Wales and Scotland
(1)
Subject to the provisions of this Order and to the requirements in Schedule 2 (requirements) Network Rail is granted development consent for the authorised development to be carried out within the Order limits.
(2)
Subject to article 8 (limits of deviation) the authorised development may only be constructed in the lines and situations shown on the works plans and in accordance with the levels shown on the sections.
Annotations
Commencement
- I1
Art. 4 in force at 6.11.2012, see art. 1