OpenLegislation

Paragraph 11 Alteration, reconstruction or replacement of level crossingsI1

England, Wales and Scotland

(1)

Within 12 months of the commencement of the operation of the authorised development a report on the optimisation of the operation and risk assessments of the level crossings on the Askern Line between the authorised development and the Norton level crossing must be submitted to, and agreed in writing by, the F1Office of Rail and Road and made available to the relevant local highway authority.

(2)

Before commencement of the removal of the level crossing at Honey Lands Lane a report on the amendments to and risk assessment of the Owston Grange Farm No. 1 crossing both during construction and in final operational form must be submitted to, and agreed in writing by, the Office of Rail and Road and made available to the relevant highway authority.

Annotations

Textual amendments

F1

Words in Sch. 2 para. 11 substituted (16.10.2015) by The Office of Rail Regulation (Change of Name) Regulations 2015 (S.I. 2015/1682), reg. 1(2), Sch. para. 10(hh) (as extended to U.K. (29.7.2016) by virtue of by S.I. 2016/645, reg. 1(1), Sch. 1 para. 5 (with reg. 4))

Commencement

I1

Sch. 2 para. 11 in force at 6.11.2012, see art. 1