Schedule 7 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1
England, Wales and Scotland
(1) Area | (2) Number of land on Order plans | (3) Purposes for which temporary possession may be taken | (4) Authorised Work |
|---|---|---|---|
| County of Warwickshire | |||
| Borough of Nuneaton and Bedworth | 3A, 3B | Worksite | Work No. 3 |
| 4 | Worksite and access for construction | Works Nos. 1 and 2 | |
| 9 | Worksite and access for construction | Works Nos. 1, 2, 3 and 4 | |
| 12 | Repairs to and strengthening of bridge and access across the bridge for construction | Works Nos. 1, 2 , 3 and 4 | |
| 13, 14, 15 | Worksite and access for construction | Bridge repair and strengthening | |
| Works Nos. 1, 2, 3 and 4 | |||
| 18 | Worksite | Works Nos. 1 and 2 | |
| 23 | Vehicle holding area | Works Nos. 1, 2, 3 and 4 | |
| 27, 28, 29, 30, 31, 32 | Construction of Work No. 4 | Work No. 4 | |
Annotations
Commencement
- I1
Sch. 7 in force at 20.7.2010, see art. 1