OpenLegislation

Schedule 10 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1

England, Wales and Scotland

(1)

Area

(2)

Number of land shown on the land plans

(3)

Purpose for which temporary possession may be taken

(4)

Relevant part of the authorised works

Metropolitan district of the City of ManchesterPlots 1, 2, 4 and 5Worksite and access for construction of the authorised worksWorks Nos. 1 and 2
Metropolitan district of the City of ManchesterPlots 6 and 204Worksite and access for construction of the authorised worksWork No. 1
Metropolitan district of the City of ManchesterPlots 9, 10, 11, 13, 14, 15, 17, 21, 24, 25, 26, 27, 29 and 30Worksite and access for construction of the authorised worksWorks Nos. 1 and 2
Metropolitan district of the City of ManchesterPlots 47, 50, 58 and 59Worksite and access for construction of the authorised worksWorks Nos. 1, 2 and 5
Metropolitan district of the City of SalfordPlots 76, 95 and 98Worksite and access for construction of the authorised works and construction of a new footpath and cycletrack within plot 95Works Nos. 1, 2 and 5
Metropolitan district of the City of ManchesterPlots 65, 72 and 73Worksite and access for construction of the authorised worksWorks Nos. 1 and 4
Metropolitan district of the City of SalfordPlots 80, 81, 93, 106, 126, 130, 132 and 137Worksite and access for construction of the authorised worksWorks Nos. 1, 2 and 4
Metropolitan district of the City of SalfordPlots 145, 160, 165, 166,169, 170, 174, 175, 184 and 203Worksite and access for construction of the authorised worksWorks Nos. 1 and 3

Annotations

Commencement

I1

Sch. 10 in force at 21.4.2015, see art. 1