OpenLegislation

Paragraph 13 TreesI1

England, Wales and Scotland

(1)

The authorised development may not be commenced until Network Rail has provided to the relevant planning authority and the relevant planning authority has approved a plan indicating trees within the Order limits that have to be removed for the construction of the authorised development. No trees except for those identified on the approved plan may be removed for the construction of the authorised development without the consent of the relevant planning authority.

(2)

The plan submitted must also identify areas of tree protective fencing to be erected prior to commencement of the authorised development. The fencing shown on the approved plan is to be maintained during the construction period to the reasonable satisfaction of the relevant planning authority. At the end of the construction period, the fencing must be removed in total to the satisfaction of the relevant planning authority.

Annotations

Commencement

I1

Sch. 1 Pt. 2 para. 13 in force at 21.11.2013, see art. 1