OpenLegislation

Paragraph 7 Re-use of excavated materialsI1

England, Wales and Scotland

The authorised development must not be commenced until Network Rail has agreed with the relevant planning authority a scheme for the recovery and re-use of excavated material in accordance with principles set out in section 4 of the waste management plan. The scheme must in particular have regard to the principles set out in paragraph 4.1 of the waste management plan.

Annotations

Commencement

I1

Sch. 1 Pt. 2 para. 7 in force at 21.11.2013, see art. 1