Paragraph 1 InterpretationI1
England, Wales and Scotland
In this Part of this Schedule—
-
“the CR-E” means Network Rail’s Contract Requirements – Environment, Issue 6, September 2011;
-
“culvert 11” means the culvert referred to as culvert 11 on the engineering plans including existing services and new services, drainage and surface water management;
-
“culvert 13” means the culvert referred to as culvert 13 on the engineering plans including existing services and new services, drainage and surface water management;
-
“the Historic Environment Planning Officer” means the Historic Environment Planning Officer for the County of Worcestershire; and
-
“operational railway land” means land required permanently for the construction of Work No. 1 and any existing railway corridor including associated works, structures, embankments, cuttings, bridges and culverts.
Annotations
Commencement
- I1
Sch. 1 Pt. 2 para. 1 in force at 21.11.2013, see art. 1