OpenLegislation

Part 2 Scenario 2I1

England and Wales

(1) Area(2) Number of land shown on land plan(3) Purpose for which temporary possession may be taken(4) Part of the authorised project
District of North Norfolk01/01, 01/02, 01/03, 01/04, 01/05, 01/06, 01/07, 01/08, 01/09, 01/10, 01/11, 01/12, 01/13, 01/17, 01/18, 01/19, 01/20, 02/01, 02/02 and 02/03Facilitating construction and carrying out the authorised project; construction compounds for carrying out the authorised project; access for carrying out the authorised project.Work Nos. 4B, 4C and 5
District of North Norfolk02/04, 02/05, 02/09, 02/11, 02/12, 02/13, 02/14, 02/16, 02/18, 02/19, 02/21, 02/22, 02/23, 03/01, 03/02, 03/04, 03/05, 03/06, 03/07, 03/08, 03/09, 03/10, 03/11, 03/13, 04/01, 04/02, 04/03, 04/05, 04/08, 04/09, 04/10, 04/11, 04/12, 05/01, 05/03, 05/04, 05/06, 05/07, 05/08, 05/10, 06/01, 06/02, 06/03, 06/04, 06/05, 06/10, 06/14, 07/01, 07/03, 07/04, 07/06, 07/09, 07/10, 08/02, 08/05, 08/08, 08/10, 08/13, 08/15, 08/17, 08/19, 08/20, 08/21, 08/23, 09/03, 09/07, 09/08, 09/11, 09/12, 09/15, 09/16, 10/01, 10/02, 10/04, 10/05, 10/11, 10/14, 10/15, 10/16, 10/17, 11/01, 11/03, 11/05, 11/06, 11/09, 11/10, 11/12, 11/13, 11/14, 12/02, 12/03, 12/04, 12/05, 12/06, 12/10, 13/02, 13/05, 13/08, 13/09, 13/10, 13/11, 13/13, 14/02, 14/03, 14/04 and 14/05Facilitating construction and carrying out the authorised project; carrying out the authorised project; access for carrying out the authorised project.Work No. 4A, 4B, 4C and 5
District of North Norfolk01/14, 01/15, 01/16, 02/06, 02/07, 02/08, 02/10, 02/15, 02/17, 02/20, 03/03, 03/12, 04/04, 05/02, 05/05, 05/09, 05/11, 06/06, 06/08, 06/09, 06/11, 06/13, 07/02, 07/05, 07/07, 07/08, 07/12, 08/03, 08/04, 08/06, 08/12, 09/06, 09/09, 09/10, 09/13, 09/14, 10/07, 10/08, 10/09, 11/02, 11/04, 11/07, 11/08, 11/11, 11/15, 12/01, 12/07, 12/09, 13/01, 13/04, 13/06, 13/07, 13/12, 14/01 and 14/06Laying of hardstanding and improvements to tracks; access for carrying out the authorised project.Work Nos. 4B, 4C, 5 and 6
District of North Norfolk04/06, 04/07, 06/07, 06/12, 07/11, 08/01, 08/07, 08/09, 08/11, 08/14, 08/16, 08/18, 08/22, 08/24, 09/01, 09/02, 09/04, 09/05, 10/03, 10/06, 10/10, 10/12, 10/13, 12/08, 12/11, 13/03, 14/08, 14/10, 14/14, 14/21, 14/23, 14/25, 14/28, 15/01, 15/06, 15/09, 18/03, 18/15, 18/16, 20/21, 21/02, 21/06, 21/10, 21/11, 21/17, 23/04, 23/10, 23/12, 24/09, 24/12, 27/03, 27/12, 28/06, 28/07, 28/09, 28/10, 29/01, 29/03, 29/04, 29/06, 31/10, 33/05, 33/07, 33/09, 33/10, 33/13, 33/17, 34/02, 34/12, 35/02, 35/08, 35/10, 35/14, 36/19, 37/03, 37/04, 37/06, 37/10, 0137/12 and 37/15Facilitating construction and carrying out works including crossings and drill works; mobilisation zone for construction and laydown and carrying out the authorised project; access for carrying out the authorised project.Work Nos. 4C and 5
Districts of North Norfolk and Broadland14/07Facilitating construction and carrying out the authorised project; carrying out the authorised project; access for carrying out the authorised project.Work Nos. 5 and 6
Districts of North Norfolk and Broadland14/08, 19/05Facilitating construction and carrying out the authorised project; trenchless crossing zone for construction and laydown and carrying out the authorised project; access for carrying out the authorised project.Work Nos. 5 and 6
District of Broadland14/07, 14/09, 14/12, 14/15, 14/18, 14/20, 14/26, 14/27, 15/02, 15/03, 15/04, 15/05, 15/07, 15/11, 15/13, 15/15, 16/03, 16/05, 16/08, 16/09, 16/10, 16/12, 16/13, 17/01, 17/02, 17/03, 17/04, 17/05, 17/07, 18/01, 18/02, 18/04, 18/05, 18/08, 18/13, 18/14, 19/04, F1... 19/07, 20/01, 20/02, 20/03, 20/06, 20/07, 20/09, 20/10, 20/17, 20/19, 20/20, 21/01, 21/03, 21/08, 22/01, 22/03, 22/04, 22/05, 22/06, 22/07, 22/12, 22/13, 22/14, 22/15, 23/01, 23/03, 23/05, 23/06, 23/07, 23/08, 23/09, 23/11, 23/13, 23/14, 24/01, 24/04, 24/05, 24/08, 24/10, 24/11, 24/16, 24/19, 25/02, 25/04, 25/06, 25/07 and 26/01Facilitating construction and carrying out the authorised project; carrying out the authorised project; access for carrying out the authorised project.Work No. 6
District of Broadland14/11, 14/13, 14/16, 14/19, 14/22, 14/24, 15/08, 15/10, 15/12, 15/14, 16/01, 16/02, 16/04, 16/06, 16/07, 16/11, 16/14, 17/06, 18/06, 18/07, 18/09, 18/10, 18/11, 18/12, 19/01, 19/02, 19/03, 19/06, 19/08, 19/09, 20/04, 20/05, 20/08, 20/11, 20/18, 21/04, 21/04, 21/05, 21/07, 21/09, 21/12, 21/13, 21/14, 21/15, 21/16, 22/02, 22/08, 22/09, 22/10, 22/11, 22/16, 23/02, 24/02, 24/03, 24/06, 24/07, 24/13, 24/14, 24/15, 24/17, 24/18, 25/01, 25/03, 25/05, 26/02 and 26/04Laying of hardstanding and improvements to tracks; access for carrying out the authorised project.Work Nos. 5, 6 and 7
Districts of Broadland and Breckland26/03Facilitating construction and carrying out the authorised project; carrying out the authorised project; access for carrying out the authorised project.Work Nos. 6 and 7.
District of Breckland26/05, 26/06, 26/08, 26/10, 26/11, 26/13, 27/02, 27/04, 27/06, 27/13, 28/04, 28/05, 29/07, 29/09, 29/10, 29/12, 30/02, 30/03, 30/04, 30/05, 30/06, 30/10, 30/11, 31/02, 31/03, 31/04, 31/05, 32/02, 32/03, 32/06, 32/09, 32/12, 32/13, 32/14, 32/15, 33/02, 33/03, 33/04, 33/12, 34/03, 34/04, 34/08, 34/09, 34/10, 34/11, 34/13, 35/11, 35/12, 36/02, 36/05, 36/06, 36/08, 36/09, 36/10, 36/11, 36/14, 36/15, 36/16, 36/17, 36/21, 37/05, 37/13, 37/14, 38/02, 38/03, 38/05, 38/06, 38/08, 38/12, 39/04, 39/05, 39/06, 39/07, 39/15, 39/16, 40/02, 40/03, 41/08, 41/10, 41/11, 41/13, 41/16 and 41/22Laying of hardstanding and improvements to tracks; access for carrying out the authorised project.Work Nos. 6, 7
District of Breckland26/07, 26/09, 26/12, 26/14, 26/15, 27/01, 27/05, 27/07, 27/08, 27/09, 27/10, 27/11, 27/14, 27/15, 27/16, 28/01, 28/02, 28/03, 28/08, 29/02, 29/08, 29/11, 29/13, 30/01, 30/07, 30/08, 30/09, 30/12, 31/01, 31/06, 31/07, 31/08, 31/09, 31/11, 31/12, 31/13, 32/01, 32/04, 32/05, 32/07, 32/08, 32/10, 32/11, 33/01, 33/06, 33/08, 33/08, 33/11, 33/14, 33/15, 33/16, 34/01, 34/05, 34/06, 34/07, 35/01, 35/03, 35/04, 35/05, 35/06, 35/07, 35/09, 35/13, 35/15, 35/16, 36/01, 36/03, 36/04, 36/07, 36/12, 36/13, 36/18, 36/20, 37/01, 37/02, 37/07, 37/08, 37/09, 37/11, 37/16, 37/17, 37/18, 37/19, 37/20, 37/21, 37/22, 38/01, 38/04, 38/07, 38/09, 38/11, 39/01, 39/02, 39/03, 39/09, 39/10, 39/12 and 39/13Facilitating construction and carrying out the authorised project; carrying out the authorised project; access for carrying out the authorised project.Work Nos. 7
District of Breckland40/01, 40/04, 40/11, 40/12, 40/14, 41/03a, 40/15a, 40/23, 40/26, 40/27, 40/31, 40/33a, 41/01a, 41/03, 41/03b, 41/14a, 41/14c, 41/28, 41/30b, 41/30c, 41/30d, 41/33, 41/40, 40/15b, 41/14, 41/15, 41/15a, 41/05, 41/14b, 41/14d, 41/14e, 41/23, 41/23a, 41/24 and 41/25Facilitating construction and carrying out the authorised project; carrying out the authorised project; access for carrying out the authorised project.Work Nos. 7, 8A, 8B, 9, 10A, 10B, 10C, 11A(E), 11A(W), 12B
District of Breckland40/31a, 40/15d, 40/20a, 40/17a, 40/20, 40/26a, 40/27a, 40/28, 40/31a, 40/32, 40/33 and 40/33bFacilitating construction and carrying out Work Nos. 7, 8A, 8B, 8B, 9 and 12B, construction and laydown and carrying out the authorised project; access for carrying out the authorised project.Work Nos. 7, 8A, 8B, 9, 10A, 10B, 10C, 11A(E), 11A(W), 12B
District of Breckland41/01, 41/01b, 41/07, 41/09, 41/09a, 41/09b, 41/17, 41/17a, 41/18, 41/18a, 41/12, 41/27, 41/30, 41/30e, 41/30f, 41/39, 41/40a, 41/41, 41/42, 41/43, 41/44, 41/45, 41/46, 41/47 and 41/48Facilitating construction and carrying out Work Nos. 10C, 11A(W), 11A(E), 11B, construction and laydown and carrying out the authorised project; access for carrying out the authorised project.Work Nos. 10C, 11A(W), 11A(E), 11B
District of Breckland42/02, 42/03, 42/04, 42/05 and 42/06Facilitating construction and carrying out Work Nos. 10C and 12B, construction and laydown and carrying out the authorised project; access for carrying out the authorised project.Work Nos. 10C and 12B

Annotations

Textual amendments

F1

Word in Sch. 8 Pt. 2 omitted (12.8.2022) by virtue of The Norfolk Boreas Offshore Wind Farm (Corrections) Order 2022 (S.I. 2022/901), art. 1(2), Sch.

Commencement

I1

Sch. 8 Pt. 2 in force at 1.1.2022, see art. 1