OpenLegislation

Paragraph 2 I1

England and Wales

(1)

Such activities are authorised in relation to the construction, maintenance and operation of (in the event of scenario 1 and scenario 2 unless otherwise stated below)—

Work No. 1 (phase 1) in the event of scenario 1 and scenario 2—

(a)

an offshore wind turbine generating station with an electrical export capacity of up to 1,800 MW at the point of connection to the offshore electrical platform(s) referred to at Work No. 2 comprising up to 158 wind turbine generators each fixed to the seabed by one of the following foundation types: monopile (piled or suction caisson), jacket (piled or suction caisson), gravity base or tetrabase fitted with rotating blades and situated within the area shown on the works plan and further comprising (b) to (e) below;

(b)

up to one offshore service platform fixed to the seabed within the area shown on the works plan by one of the following foundation types: jacket (piled or suction caisson) or gravity base;

(c)

up to two meteorological masts fixed to the seabed within the area shown on the works plan by one of the following foundation types: monopile (piled or suction caisson), jacket (piled or suction caisson) or gravity base;

(d)

up to two LIDAR measurement buoys fixed to the seabed within the area shown on the works plan by one of the following foundation types: monopile (piled) or floating and up to two wave measurement buoys fixed to the seabed within the area shown on the works plan by one foundation type (floating); and

(e)

a network of subsea array cables and fibre optic cables within the area shown on the works plan between the wind turbine generators, and between the wind turbine generators and Work No.2 including one or more offshore cable crossings.

In the event of scenario 1—

(f)

a network of subsea cables and fibre optic cables connecting wind turbine generators within (a) above to an offshore electrical platform within Norfolk Vanguard East including one or more offshore cable crossings.

(2)

In connection with such Work No. 1 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised scheme and which fall within the scope of the work assessed by the environmental statement and the provisions of this licence including:

(a)

scour protection around the foundations of the offshore structures;

(b)

cable protection measures such as the placement of rock and/or concrete mattresses, with or without frond devices;

(c)

the removal of material from the seabed required for the construction of Work No. 1 and the disposal of up to a total of 37,698,890 m3 of inert material of natural origin within the Order limits produced during construction drilling, seabed preparation for foundation works, cable installation preparation such as sandwave clearance, boulder clearance and pre–trenching and excavation of horizontal directional drilling exit pits; and

(d)

removal of static fishing equipment;

(3)

In connection with such Work No. 1, ancillary works within the Order limits which have been subject to an environmental impact assessment recorded in the environmental statement comprising—

(a)

temporary landing places, moorings or other means of accommodating vessels in the construction and/ or maintenance of the authorised scheme; and

(b)

beacons, fenders and other navigational warning or ship impact protection works.

Annotations

Commencement

I1

Sch. 9 Pt. 3 para. 2 in force at 1.1.2022, see art. 1