Paragraph 3 Design parametersI1

England and Wales

The total length of the cables and the area and volume of their cable protection must not exceed the individual distributions set out in Table 2 of the outline scour protection and cable protection plan and must not exceed the following—

WorkLengthCable protection (m3)Cable protection (m2)
Work No. 1(e) and (f) (array)600 kilometres198,500 m3389,000 m2

Annotations

Commencement

I1

Sch. 9 Pt. 4 para. 3 in force at 1.1.2022, see art. 1