Paragraph 14 Safeguarding of watercourses and drainageI1
England, Wales and Scotland
No part of any numbered work in Schedule 1 (authorised development) is to commence until a written scheme for the provision and implementation of pollution control relevant to the construction of that numbered work has been submitted to and, following consultation with the relevant district authorities and the Environment Agency, approved in writing by the relevant planning authority.
The written scheme must include the following, which must comply with or include relevant measures or details set out in the environmental statement—
details of measures for the collection, treatment and disposal of all water entering or arising on the Order land;
details of measures for the collection and disposal of foul drainage; and
details of measures for the storage of any chemicals, oil or fuel.
The approved scheme must be implemented in full.
Annotations
Commencement
- I1
Sch. 2 para. 14 in force at 23.6.2015, see art. 1