Introductory text
Infrastructure Planning
Made 18th December 2025
Coming into force 19th December 2025
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008f1, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2 for non-material changes to the Norfolk Vanguard Offshore Wind Farm Order 2022f3.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f4, has decided to make the changes on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order.
Annotations
Footnotes
- f1
-
2008 c. 29. Paragraph 2 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 to the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015 (c. 7). There are other amendments to the Act that are not relevant to this Order.
- f2
-
S.I. 2011/2055, as amended by S.I. 2012/635, S.I. 2013/522, S.I. 2015/760, S.I. 2017/314, S.I. 2017/524, S.I. 2018/378, S.I. 2019/734, S.I. 2020/1534, S.I. 2022/634 and S.I. 2023/1071.
- f3
-
S.I. 2022/138, as amended by S.I. 2022/944, S.I. 2022/1004 and S.I. 2023/1390.
- f4
-
S.I. 2011/2055. Regulations 6 and 7 were both amended by S.I. 2012/635, S.I. 2015/760, S.I. 2020/1534 and S.I. 2020/764.