Paragraph 32 Operational drainage planI1

England, Wales and Scotland

(1)

Each of Work No. 8A and Work No. 8B and Work No. 10A, Work No. 10B, and Work No. 10C must not commence until a written plan for drainage during operation of the relevant work, has been submitted to and approved by the relevant planning authority, following consultation with Norfolk County Council and the Environment Agency.

(2)

The operational drainage plan must accord with the principles for the relevant work set out in the outline operational drainage plan, and must include a timetable for implementation.

(3)

The operational drainage plan must be implemented as approved.

Annotations

Commencement

I1

Sch. 1 para. 32 in force at 22.7.2020, see art. 1