Paragraph 1 Notification of commencement and completion

Original text. Later amendments are not shown.

(1)

The undertaker shall notify the MMO—

(a)

of its acceptance of the conditions contained in this Part 2 not less than 5 working days prior to commencement of the licensed activities or any part of them;

(b)

of its intention to commence the licensed activities not less than 5 working days prior to commencement of the licensed activities or any part of them; and

(c)

of completion of the authorised development within 10 working days of such completion having occurred.

(2)

Not less than 5 working days prior to commencement of the relevant licensed activities the undertaker shall notify the MMO of any agents, contractors or subcontractors proposed to carry out the licensed activities on behalf of the undertaker and those persons notified to the MMO shall provide written confirmation to the MMO confirming their understanding of the terms and requirements of this Schedule and any subsequent amendments or revisions to it issued from time to time.

(3)

Not less than 24 hours prior to commencement of the relevant licensed activities the undertaker shall notify the MMO of any vessel (including the vessel type, vessel IMO number and vessel owner or operating company) proposed to be used to carry out the licensed activities on behalf of the undertaker and the Masters of the vessels notified to the MMO shall provide written confirmation to the MMO that a copy of the Order is held upon the vessel and confirming their understanding of the terms and requirements of this Schedule and any subsequent amendments or revisions to it.