Paragraph 187 Approvals and notice

Original text. Later amendments are not shown.

(1)

The undertaker will obtain the approval in writing of the PLA on—

(a)

any cable specification and installation plan (in so far as that plan relates to any specified work within or which may affect the Area of Interest) before any application for approval of that plan may be submitted by the undertaker in compliance with condition 22(1) of the deemed marine licence for the transmission assets in Schedule 9 and any revisions arising from such application;

(b)

any navigation and installation plan (in so far as that plan relates to any specified work within or which may affect the Area of Interest) before any application for approval of that plan may be submitted by the undertaker in compliance with condition 22(1) of the deemed marine licence for the transmission assets in Schedule 9 and any revisions arising from such application;

(c)

any sediment disposal management plan (in so far as that plan relates to any specified work within or which may affect the Area of Interest) before any application for approval of that plan may be submitted by the undertaker in compliance with condition 22(1) of the deemed marine licence for the transmission assets in Schedule 9 and any revisions arising from such application; and

(d)

any operation and maintenance plan (in so far as that plan relates to any specified work within or which may affect the Area of Interest) before any application for approval of that plan may be submitted by the undertaker in compliance with condition 12(4) of the deemed marine licence for the transmission assets in Schedule 9 and any revisions arising from such application.

(2)

The undertaker will consult the PLA on the proposed activities and programme for any pre-construction monitoring, construction monitoring, post construction monitoring and related reporting within the Area of Interest no less than 20 business days before such survey work is programmed to commence. The undertaker must have regard to any request made by the PLA for reasonable amendment to the proposed activities or programme, which request must be made to the undertaker within five business days of receipt of the details of the proposed activities and programme.

(3)

The undertaker must notify the PLA of the final planned programme for any pre-construction monitoring, construction monitoring, and post construction monitoring within the Area of Interest no less than five business days before such survey work is programmed to begin.

(4)

The undertaker will consult the PLA on any application for marine licensing for the clearance of unexploded ordnance within or which may affect the Area of Interest before such applications are submitted to the MMO. The undertaker must have regard to any request made by the PLA for reasonable amendment to the proposed application, which request must be made to the undertaker within 10 business days of receipt of the details of the proposed application.

(5)

The undertaker must notify the PLA of the final programme for any clearance of unexploded ordnance to be undertaken within, or which may affect, the Area of Interest no less than 20 business days before such disposal is programmed to begin.

(6)

The undertaker will consult the PLA on the activities and programme for any specified work to be undertaken under this Order which is not covered by the cable specification and installation plan and which is within or may affect the Area of Interest no less than 20 business days before such specified work is programmed to commence. The undertaker must have regard to any request made by the PLA for reasonable amendment to the activities or programme.

(7)

The undertaker must notify the PLA of the final method statement and programme for any specified work to be undertaken under this Order which is not covered by the cable specification and installation plan and which is within or may affect the Area of Interest no less than five business days before such work is programmed to begin.