Paragraph 188 Cable Specification and Installation Plan

Original text. Later amendments are not shown.

The cable specification and installation plan referred to in paragraph 187 must be informed by a cable burial risk assessment for Work No. 3 to include—

(a)

in so far as it applies to the Deep Water Routes demonstrate compliance with requirement 2(3) that any part of Work No. 3, any associated development or ancillary works located within the Area of Interest as shown shaded yellow on the Deep Water Route Cable Installation Area (Future Dredging depths) plan must be installed at a level which would not preclude or impede the dredging of those parts of the Deep Water Routes—

(i)

shown shaded in orange and labelled Sunk A – Sunk DW Buffer, to a level of 22 metres below Chart Datum;

(ii)

shown shaded in pink and labelled Trinty – Trinity DW Buffer, to a level of 22 metres below Chart Datum;

(iii)

shown shaded in green and labelled Sunk B – Sunk DW Buffer, to a level of 19 metres below Chart Datum; and

(iv)

shown shaded in blue and labelled Sunk Pilotage Area – Sunk Pilot Diamond Buffer, to a level of 22 metres below Chart Datum;

(b)

the proposed cable installation methods and measures for management of construction risks;

(c)

additional cable burial depths required or any other forms of cable protection proposed including type, volume and locations;

(d)

during construction of the cables and cable protection in the Area of Interest arrangements for the consultation of the PLA in a timely manner, on such matters regarding those works as the PLA may reasonably request including arrangements for providing the PLA with a point of contact for continuing liaison and co-ordination throughout the construction of these works;

(e)

the proposed programme of work for cable installation and arrangements for notification of any changes to the programme to the PLA;

(f)

the programme and methodologies for monitoring and the arrangements for the results of these surveys or other construction evidence being made available to the PLA within 10 business days of the undertaker receiving reports of the survey results; together with methods and timescales to rectify any issues which may compromise the level referred to requirement 2(3) or evidence to demonstrate compliance with the depths referred to in requirement 2(3);

(g)

methods and timescales to rectify any issues which may compromise the depth referred to in requirement 2(3);

(h)

a requirement for a process (subject to Condition 39 Remediation, Schedule 9) and timescales (both the undertaker and the PLA acting reasonably) for cable re-installation should the level of the cable be such that the under keel clearance specified in Outline CSIP cannot be achieved over the lifetime of the authorised development.